Do we have a suitable product to smooth over a newly installed sand/cement screed? Do we have a suitable product to smooth over a newly installed sand/cement screed?

Do we have a suitable product to smooth over a newly installed sand/cement screed?

New sand and cement screeds should be left for 3 weeks before any work is carried out. Where a sand and cement screed is over a DPM further down in the underlying substrate then a moisture suppressant can be used for screeds up to 95% RH called Ardex MVS95. 
For further information contact Ardex Technical Dept.